Project Management Professional (PMP) Exam Practice – Question1150

A team is working on a project to address a customer's incomplete records. A list of the customer's files is created, and the team begins work. During the project, a key stakeholder asks that another small group of incomplete records be added to the list.
What should the project manager do?


A.
Refuse the request.
B. Add the small group of records to the list.
C. Make a decision based on the project sponsor's opinion.
D. Issue a change request, and evaluate the impact with the project team.

Correct Answer: D