Project Management Professional (PMP) Exam Practice – Question1152


According to the information in the grid, what is the estimate at completion (EAC) for this project and what does it represent?


A.
US$9,000 -the original project budget
B. US$13,500 -the revised estimate for total project cost (based on performance to date)
C. US$13,500 -the original project budget
D. US$9,000 -the revised estimate for total project cost (based on performance to date)

Correct Answer: D