Project Management Professional (PMP) Exam Practice – Question1153

Two team members argue about who will perform and report the status of a particular task. What source may be consulted to help resolve this?


A.
Work breakdown structure (WBS)
B. Team members functional managers
C. Responsible, accountable, consult, and inform (RACI) matrix
D. Project sponsor

Correct Answer: C