A project owner requests a scope change that will cost US$10,000. While performing an assessment of the change, the project manager identifies that the change fails to add value. Still, the project owner insists that the change must be done.
What should the project manager do?


A.
Ask the project management office (PMO) for recommendations.
B. Implement the change.
C. Submit a change request to the change control board (CCB).
D. Request a subject matter expert (SME) to review the request.

Correct Answer: A