In a control chart, three measurement points in a process are below the mean and within control limits. Four measurement points are above the mean and outside the control limits.
How is this process performing?


A.
The process is out of control.
B. The process is under the seven-point rule.
C. The process is within specification limits.
D. The process is under control.

Correct Answer: D