Project Management Professional (PMP) Exam Practice – Question1158

A supplier delivers equipment that fails to meet customer requirements. Investigation determines that the supplier misunderstood the requirements and made incorrect assumptions without clarifying them with the customer.
What communication method should the project manager have used to avoid this?


A.
Interactive
B. Push
C. Pull
D. Active listening

Correct Answer: A