Project Management Professional (PMP) Exam Practice – Question1159

An issue with a critical task is blocking a project's progress. The contingency plan does not provide a solution, and team members are in disagreement about the best way to proceed.
What should the project manager do?


A.
Brainstorm ideas using the nominal group technique.
B. Gather ideas using affinity diagrams.
C. Seek intervention from the project sponsor.
D. Apply mind mapping techniques.

Correct Answer: A