Project Management Professional (PMP) Exam Practice – Question1160

A project's most recent status report indicates a schedule performance index (SPI) of 1.1 and a cost performance index (CPI) of 1.2. A key stakeholder then suggests a change to include a value-added feature that would not impact project schedule and cost.
What should the project manager do next?


A.
Evaluate the change's impact with the team.
B. Advise the stakeholder that changes should not be implemented when a project is behind schedule.
C. Update the project management plan to include the new feature.
D. Advise the stakeholder that, since the project is under budget, the feature will be added.

Correct Answer: A