Project Management Professional (PMP) Exam Practice – Question1168

Scope, schedule, and cost parameters are integrated in the:


A.
Performance measurement baseline.
B. Analysis of project forecasts,
C. Summary of changes approved in a period,
D. Analysis of past performance.

Correct Answer: A