Project Management Professional (PMP) Exam Practice – Question1178

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:


A.
Work performance information.
B. Inspections and audits.
C. Payment systems.
D. Procurement performance reviews.

Correct Answer: D