Project Management Professional (PMP) Exam Practice – Question1190 Which tool or technique is used to manage change requests and the resulting decisions? A. Change control tools B. Expert judgment C. Delphi technique D. Change log Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question1189Project Management Professional (PMP) Exam Practice – Question1191