Project Management Professional (PMP) Exam Practice – Question1194 Reserve analysis is a tool and technique used in which process? A. Plan Risk Management B. Plan Risk Responses C. Identify Risks D. Control Risks Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question1193Project Management Professional (PMP) Exam Practice – Question1195