Project Management Professional (PMP) Exam Practice – Question1195

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?


A.
External
B. Internal
C. Mandatory
D. Discretionary

Correct Answer: D