Project Management Professional (PMP) Exam Practice – Question1196

The Monitoring and Controlling Process Group includes processes that:


A.
Establish the scope, objectives, and course of action of a project,

B. Define a new project or a new phase of an existing project.
C. Track, review, and regulate the progress and performance of a project.
D. Complete the work defined in the project management plan.

Correct Answer: C