A projects latest earned value (EV) report indicates that a certain task has an estimate at completion (EAC) of US$550,000 and a budget at completion (BAC) of US$500,000.
What should the project manager experience will this task?
A. A budget overrun on completion
B. Completion under budget
C. Completion exactly on budget
D. A budget needing sponsor approval to continue
What should the project manager experience will this task?
A. A budget overrun on completion
B. Completion under budget
C. Completion exactly on budget
D. A budget needing sponsor approval to continue