Project Management Professional (PMP) Exam Practice – Question1204

One week after project deployment, a project manager unsuccessfully tries to resolve an issue on their own. The project manager failed to inform stakeholders, which resulted in their frustration.
To avoid stakeholder frustration, what should the project manager have done?


A.
Referred to the stakeholder engagement plan
B. Updated the issue log

C. Referenced the lessons learned repository
D. Adhered to the communications management plan

Correct Answer: D