Project Management Professional (PMP) Exam Practice – Question1205

A client informs the project manager that the projects testing phase must be limited to ensure timely delivery. The client explains that since the project has several components, some testing scope must be eliminated to ensure that expectations are met. The
budget must remain constant, as cost increases are not possible at this time.

What should the project manager do?


A.
Update the testing plan with the new approach, and obtain formal client approval.
B. Include a post-project delivery defect resolution, and increase the budget accordingly.
C. Continue planning with the full testing approach.
D. Plan for the fast track approach, and increase the budget.

Correct Answer: A