Project Management Professional (PMP) Exam Practice – Question1212

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?


A.
US$S000
B. US$9500
C. US$10,000
D. US$12,500

Correct Answer: D