Project Management Professional (PMP) Exam Practice – Question1214

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:


A.
training, testing, and warranty work.
B. equipment, rework, and scrap.
C. training, document processes, and inspections.
D. inspections, rework, and warranty work.

Correct Answer: C