Project Management Professional (PMP) Exam Practice – Question1215

Which of the following is a tool or technique of the Define Activities process?


A.
Rolling wave planning
B. Precedence diagramming method (PDM)
C. Alternatives analysis
D. Parametric estimating

Correct Answer: A