Project Management Professional (PMP) Exam Practice – Question1227 At the end of the project, what will be the value of SV? A. Positive B. Zero C. Negative D. Greater than one Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1226Project Management Professional (PMP) Exam Practice – Question1228