Project Management Professional (PMP) Exam Practice – Question1230

The process for performing variance analysis may vary, depending on:


A.
scenario building, technology forecasting, and forecast by analogy.
B. working relationships among various stakeholders and team members.
C. application area, the standard used, and the industry.
D. work to be completed next.

Correct Answer: C