Project Management Professional (PMP) Exam Practice – Question1233

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


A.
Reserve analysis
B. Three-point estimating
C. Parametric estimating
D. Analogous estimating

Correct Answer: D