Project Management Professional (PMP) Exam Practice – Question1242

Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?


A.
Close Procurements
B. Administer Procurements
C. Plan Procurements
D. Conduct Procurements

Correct Answer: A