Project Management Professional (PMP) Exam Practice – Question1245 Which of the following choices is a contract closure tool or technique? A. Contract plan B. Procurement plan C. Closure process D. Procurement audits Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question1244Project Management Professional (PMP) Exam Practice – Question1246