Project Management Professional (PMP) Exam Practice – Question1246

Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?


A.
Schedule performance index (SPI)
B. Cost performance index (CPI)
C. Cost variance (CV)
D. Planned value (PV)

Correct Answer: B