Project Management Professional (PMP) Exam Practice – Question1249

The Closing Process Group includes which of the following Knowledge Areas?


A.
Project Risk Management and Project Procurement Management
B. Project Integration Management and Project Procurement Management
C. Project Risk Management and Project Integration Management
D. Project Integration Management and Project Quality Management

Correct Answer: B