Project Management Professional (PMP) Exam Practice – Question1250

A project sponsor asks to terminate a software installation project that is 80 percent complete. What should the project manager do first?


A.
Follow the project management plan to close the project.
B. Meet with the sponsor to discuss the possibility of continuing the project.
C. Release the project team to other projects.
D. Proceed to complete the installation, then close the project.

Correct Answer: B