Project Management Professional (PMP) Exam Practice – Question1252

All the deliverables defined in a project have been completed. In the final meeting to approve these deliverables, some stakeholders state that the product does not meet their needs.
What should the project manager do?


A.
Demonstrate that the objectives in the project charter have been achieved.
B. Validate that the deliverables are as requested and close the project.
C. Demonstrate that the deliverables have been verified and negotiate their approval.
D. Review the list of stakeholders and determine whether the appropriate individuals attended the meeting.

Correct Answer: C