At the final project closeout meeting, the customer informs the project manager that they require only selected parts of the project information. What should the project manager do with the documentation internally?


A.
Comply with the current legislation for document retention.
B. Archive project documents per their own companys document retention policies.

C. Remove the unnecessary parts of the documentation to match the customers request.
D. Archive the entire documentation in the project management office (PMO) for retrieval upon customer request.

Correct Answer: B