Project Management Professional (PMP) Exam Practice – Question1255

A project manager is determining the accuracy of the deliverables before closing a project. What process should be used to determine this and is an input to formalizing acceptance?


A.
Control Scope
B. Manage Quality
C. Plan Scope Management
D. Control Quality

Correct Answer: A