Project Management Professional (PMP) Exam Practice – Question1259

An increase in the number of client-requested deliverables has been addressed by updating the acceptance test criteria. These new deliverables, along with increased quality testing, result in a delay in achieving project milestones.
What should the project manager do?


A.
Submit a change request to the change control board (CCB).
B. Revise the quality management plan.
C. Request additional resources to meet the updated acceptance test criteria.
D. Complete the project according to the original acceptance test criteria.

Correct Answer: C