Project Management Professional (PMP) Exam Practice – Question1260

A project is completed, and the product design packaging is delivered and accepted by the customers design engineer. However, customer payment is still unresolved due to a concern about the products warranty.
What should the project manager do next?


A.
Review the contract to ensure that all project requirements are complete.
B. Document historical information and lessons learned.
C. Coordinate payment issues with the customer.
D. Review the customer acceptance document.

Correct Answer: A