Project Management Professional (PMP) Exam Practice – Question1262

During a project, a business need changes and the project is cancelled. The project manager meets with project team members to collect information learned during the project.
Where this information should be documented?


A.
Issue log
B. Organizational process assets
C. Enterprise environmental factors
D. Status report

Correct Answer: B