Project Management Professional (PMP) Exam Practice – Question1263

A company runs multiple projects simultaneously. During a project to deliver a new product, the project manager conducted final review meetings with the project team and stakeholders to document lessons learned.
What should the project manager do next?


A.
Obtain agreement from the stakeholders to validate the scope and accept the deliverables.
B. Validate compliance with the product specifications.
C. Update the organizational process assets.
D. Document the results from multiple projects and update the business case.

Correct Answer: C