Project Management Professional (PMP) Exam Practice – Question1264

During a projects final phase, the project manager evaluates project deliverables by comparing them to a similar, completed project. The project manager notices that previous mistakes are being repeated.
What should the project manager improve to avoid future mistakes?


A.
Implementation of lessons learned management techniques
B. Definition of the project scope statement
C. Creation of the work breakdown structure (WBS)
D. Application of quality control measures

Correct Answer: A