Project Management Professional (PMP) Exam Practice – Question1265

A project manager invites stakeholders to a lessons learned meeting. The stakeholders have different opinions and have previously raised issues.
What tool or technique can the project manager use to constructively engage the stakeholders?


A.
Affinity diagram
B. Questionnaires and surveys
C. Brainstorming
D. Facilitation

Correct Answer: A