During a final product demonstration, a stakeholder requests a change that is not included in the sign-off requirements. What should the project manager do?


A.
Assess the impact, and discuss it with the project sponsor.
B. Have the project team add this change to their workload.
C. Reject the stakeholders request because it is out of scope.
D. Ask the project management office (PMO) for additional funding.

Correct Answer: A