While preparing for project hand-over to the operations team, the project manager discovers that an audit report from an early project phase is missing. What should the project manager do?


A.
Update the project documents.
B. Ask the operations team to accept the project without the audit report.
C. Inform the operations team about the missing audit report.
D. Update the project management plan to remove the audit report from the required project documents list.

Correct Answer: A