Project Management Professional (PMP) Exam Practice – Question1271

As an automation project nears completion, the engineering team leader proposes adding a function that will make the production line more efficient without impacting the schedule. What should the project manager do next?


A.
Keep the original scope to meet project requirements.
B. Change the scope to meet business requirements.
C. Follow the change management plan.
D. Review the cost management plan.

Correct Answer: C