Project Management Professional (PMP) Exam Practice – Question1275

A project manager is preparing for project approval that had many changes to stakeholder requirements. There are corresponding, updated document versions of the acceptance criteria.
What should the project manager do?


A.
Request approval of the final document as soon as possible
B. Ask the key stakeholders which document version they prefer
C. Ask the sponsor to approve their preferred acceptance criteria
D. Schedule a meeting to discuss all acceptance criteria with the stakeholders

Correct Answer: D