Project Management Professional (PMP) Exam Practice – Question1276

An organization has contracts with an external supplier to support a critical part of a project. Senior management and the project team have differences about what deliverables the external supplier should provide.
What plan should be reviewed to eliminate these differences?


A.
Delivery management plan
B. Scope management plan
C. Contract management plan
D. Procurement management plan

Correct Answer: D