Project Management Professional (PMP) Exam Practice – Question1277

All quality controls have passed, and a project deliverable is ready to be released to the customer. However, a change request to add new quality criteria has been approved.

What should the project manager do first?


A.
Update the project management plan.
B. Stop the release of the deliverable to the customer.
C. Use the new quality criteria for future deliverables.
D. Update the risk register.

Correct Answer: A