Phase two of a complex, multi-phase project is completed, and the customer accepts the deliverables. What should the project team do to benefit from this phase?
A. Measure customer satisfaction.
B. Perform a risk analysis.
C. Obtain additional resources:
D. Document and share lessons learned.
A. Measure customer satisfaction.
B. Perform a risk analysis.
C. Obtain additional resources:
D. Document and share lessons learned.