To begin transitioning the final deliverables to the client, a project manager develops the project closure documentation. What should be used to develop the project closure documentation?
A. Project management plan and preliminary releases
B. Accepted deliverables and preliminary releases
C. Organizational process assets and project management plan
D. Accepted deliverables and project charter
A. Project management plan and preliminary releases
B. Accepted deliverables and preliminary releases
C. Organizational process assets and project management plan
D. Accepted deliverables and project charter