A project manager invites stakeholders to a gate review meeting. What should be done at this meeting?


A.
Evaluate if the project has met its objectives and agree on phase closure.
B. Evaluate project risks, and move on to the next project phase.
C. Ensure that all late changes to the project have been added.
D. Ensure that the change control board (CCB) has approved the latest project changes.

Correct Answer: A