Project Management Professional (PMP) Exam Practice – Question1284

Before disbanding a project team, the project manager facilitates a lessons learned workshop. What should the project manager do next?


A.
Send project documents to the stakeholders.
B. Organize a party to celebrate the project's success.
C. Perform a post-implementation review.
D. Archive project documents using generally accepted practices.

Correct Answer: D