Project Management Professional (PMP) Exam Practice – Question1312

Following a review of the completed final project phase, customer feedback is positive and formal acceptance of the deliverable is obtained.
What is the output of this meeting?


A.
Work performance information
B. Project document updates
C. Organizational process assets updates
D. Closed procurements

Correct Answer: D