Project Management Professional (PMP) Exam Practice – Question1323

The process of formalizing acceptance of the completed project deliverables is known as:


A.
Validate Scope.
B. Close Project or Phase.
C. Control Quality.
D. Verify Scope.

Correct Answer: A