Project Management Professional (PMP) Exam Practice – Question1325 What is the number of stakeholders, if the project has 28 potential communication channels? A. 7 B. 8 C. 14 D. 16 Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1324Project Management Professional (PMP) Exam Practice – Question1326